COSCO Shipping Heavy Industry (Zhoushan) Completes Integral Lift of Main Girder for 1,100-Tonne Gantry Crane

2026-11-26 14:25
Favorite

en.Wedoany.com Reported - On November 25, the integral lift of the main girder of a new 1,100-tonne gantry crane at No. 2 Dock of COSCO Shipping Heavy Industry (Zhoushan) was completed, marking key progress in the upgrading of shipbuilding production equipment. The equipment has a rated lifting capacity of 1,100 tonnes, a rail span of 184 meters, a lifting height above rail of 80 meters, a total dead weight of approximately 5,403 tonnes, and a main girder weight of approximately 3,180 tonnes. The 470-tonne main girder of another 320-tonne gantry crane was hoisted into place on November 16. The two units are scheduled for delivery and commissioning in January 2027 and by the end of 2026, respectively.

The 1,100-tonne gantry crane is the focus of this equipment construction. Its main girder features a large span and high structural weight, and the integral lifting process requires control over the forces on the overweight component, structural deformation, and synchronization accuracy across multiple lifting points. In response to these challenges, the project team carried out specialized demonstration of the lifting scheme and technical verification calculations, and optimized the construction organization plan through multiple rounds of working-condition simulation.

The main girder lift adopted a dual-tower hydraulic synchronous lifting process. Eight hydraulic jacks with a rated lifting capacity of 450 tonnes were arranged atop the rigid-leg tower, and six jacks of the same specification atop the flexible-leg tower, connected to the main girder lifting points via steel strands and anchor discs. After the tower guy-wire systems were installed, the 14 jacks worked in coordination to lift the approximately 3,180-tonne main girder integrally to its design position. During the lifting process, the construction team carried out real-time monitoring of the forces at each lifting point, lifting displacement, and structural condition, and all indicators met the design requirements.

Once completed, the equipment will undertake operations including lifting and transporting large hull blocks, in-air turning, hull assembly, and block transfer, with a maximum single-unit tandem lifting capacity of 1,100 tonnes. Compared with lower-capacity lifting equipment, it can handle the grand assembly and integral lifting of heavier hull blocks, reducing the need to split large hull blocks and transfer them multiple times. The equipment is scheduled for delivery and commissioning in January 2027.

The other 320-tonne gantry crane is located at the block fabrication yard on the east side of Tonghai No. 2 Road of the company, with a rated lifting capacity of 320 tonnes, a rail span of 71 meters, and a lifting height of 50 meters. Its main girder, weighing approximately 470 tonnes, was hoisted into place on November 16. The project is currently continuing with subsequent equipment installation and commissioning, and delivery and commissioning are planned before the end of 2026.

The two cranes respectively serve production processes including grand assembly of large hull blocks and on-site block fabrication and transfer. Once put into use, they will expand the shipyard's lifting capacity for large components, improve material transfer conditions between different production areas, and provide equipment support for the construction of large vessels.

This equipment upgrade is being advanced in parallel with the shipbuilding energy-efficiency improvement project of COSCO Shipping Heavy Industry (Zhoushan). The project was launched in December 2025, with a total floor area of approximately 42,800 square meters. Its construction content includes the expansion of No. 2 hull workshop, the construction of shot-blasting and painting facilities and a power distribution station, and the expansion of the centralized distribution workshop. It is scheduled for completion and delivery in the first quarter of 2027. Once completed, the project will focus on enhancing the construction supporting capacity and production efficiency for 200,000- to 300,000-tonne bulk carriers.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com