153-km Herat Section of Turkmenistan's TAPI Pipeline Nears Completion

2026-11-27 08:51
Favorite

en.Wedoany.com Reported - On November 26, the official oil and gas portal of Turkmenistan released an update on the construction progress of the TAPI transnational natural gas pipeline. The 153-km pipeline section connecting Serhetabat to Herat, Afghanistan, has entered the final stage of construction, with approximately 124 km of pipeline welding and laying completed. The section is scheduled to be completed by the end of 2026, with gas supply to Herat expected to begin in early 2027.

Construction of this pipeline section began on September 11, 2024, with funding provided by the Turkmenistan side. Project progress previously published by the project company shows that construction along the route has involved pipeline welding, laying, hydrostatic testing, and the construction of natural gas metering facilities. Once the Herat section is put into operation, the project company plans to generate initial operating revenue through gas sales and to advance financing for subsequent cross-border pipeline sections.

The TAPI natural gas pipeline is planned to have a total length of approximately 1,800 km, with gas sourced from Turkmenistan's Galkynysh gas field. The route passes through Herat and Kandahar in Afghanistan and Quetta and Multan in Pakistan, ultimately connecting to the Indian natural gas market. According to the phased construction plan published by the Asian Development Bank, Phase I is designed with an annual gas transmission capacity of 11 billion cubic meters, and Phase II will involve the construction of 6 compressor stations in Afghanistan and Pakistan, raising the annual gas transmission capacity to 33 billion cubic meters.

In terms of downstream supporting facilities, Turkmenistan and Afghanistan have designated the Herat industrial park natural gas trunk pipeline, natural gas distribution stations, industrial gas supply facilities, and compressed natural gas production facilities as priority projects.

The Asian Development Bank continues to monitor the TAPI project, with subsequent financing decisions depending on project implementation conditions and related assessments. Pakistan continues to follow the construction of the cross-border pipeline and has proposed supporting project concepts for transporting Turkmenistan natural gas to Gwadar Port and Karachi Port for further liquefied natural gas exports.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com