Hot Testing of Second Taipingling Unit Completed
Wedoany.com Report-Aug. 2, China General Nuclear (CGN) announced the successful completion of hot functional tests at Unit 2 of the Taipingling nuclear power plant in Guangdong, China. “On 30 July, with the drainage of the primary circuit of Unit 2 of the Taipingling nuclear power plant to the circuit water level and the successful completion of the last test of Phase II.3, it marked the successful completion of the hot performance test, and the unit took another step towards the goal of high-quality commissioning,” CGN stated.
These tests, which simulate the temperature and pressure conditions of normal reactor operation, verify that the reactor coolant system, safety systems, and other components function as designed. Conducted prior to fuel loading, the hot tests ensure that both nuclear and conventional systems meet operational requirements. Earlier this year, Unit 2 completed cold functional tests to confirm the proper installation and leak-tightness of critical components, marking the first integrated operation of reactor and auxiliary systems.
The Taipingling facility is planned to include six HPR1000 (Hualong One) reactors. Construction of Units 1 and 2 began in 2019 and 2020, respectively. Unit 1 completed its hot testing in September 2024 and is scheduled to start operations in 2025, with Unit 2 expected to follow in 2026. The project’s second phase, involving Units 3 and 4, received approval from China’s State Council on 29 December 2023, with construction of Unit 3 starting in June this year.
The completion of these tests at Unit 2 represents a significant milestone in advancing the Taipingling plant’s development. The Hualong One reactors are designed to enhance China’s nuclear energy capabilities, contributing to the country’s energy infrastructure and supporting sustainable energy goals. The ongoing progress at Taipingling underscores CGN’s commitment to ensuring high standards in the construction and commissioning of its nuclear facilities.
Related Products

YB □ -12/0.4/1250 Outdoor Prefabricated Substation (European Style)
Shangrao Shangyu Intelligent Electric Co., Ltd.
CAP1400 main feedwater flow nozzle flowmeter.
Jiangsu Hongda Instrument Technology Co., LTD.

1000kV Jin Southeast-Nanyang-Jingmen UHV AC Transmission and Transformation Pilot Demonstration Project
Anhui Hongyuan Steel Tower Co., Ltd.

5012kWh DC Energy Storage System TD-EES-5012kWh
Suzhou Tongding Xindong Energy Storage Technology Co., Ltd.
HI-Pro Green Hydrogen High-efficiency Production System-HI-PRO-AEM
Hydrizon Technology (Beijing) Co., Ltd.



220kV and Below Voltage Level Energy-saving Oil-immersed Power Transformers
FuZhou TianYu Electric Co., Ltd.