Wedoany.com Report on Mar 16th, Following the Spring Festival holiday, the Municipal Group Machinery Company swiftly organized the resumption of work on the Jiangbi Road municipal road renovation project, with the construction site presenting a bustling scene. To ensure the safe and orderly progress of the project, the company conducted comprehensive maintenance and repairs on various construction machinery such as excavators, loaders, rollers, water sprinklers, and dump trucks in advance. A detailed inspection of key components including hydraulic systems, engines, electrical circuits, and brakes was carried out to ensure the equipment is in good condition for municipal road construction. Simultaneously, the company organized pre-job safety training for all staff, explaining operational standards in conjunction with the specific characteristics of municipal road construction, guiding construction personnel to quickly return to their working state.

As a major municipal road traversing the Echeng District, the Jiangbi Road renovation project spans approximately 3.12 kilometers, with a road red line width of 50 meters, designed as a two-way six-lane road. Through integrated renovation of the road, drainage, traffic, and greenery, the project systematically addresses municipal road defects and aging pipeline networks. At the construction site, excavators extend their mechanical arms for earth excavation and roadbed leveling, loaders efficiently transport sand and gravel materials, water sprinklers operate continuously to suppress dust, and various machines coordinate effectively, with all construction phases progressing in an orderly manner. The project department ensures the quality and safety of municipal road construction through detailed technical briefings and on-site supervision throughout the entire process.
According to previous reports, the eastern half of Jiangbi Road completed asphalt paving and opened to traffic on February 11th, with the entire road temporarily opened during the Spring Festival to facilitate public travel. According to the project plan, construction will shift to the closed construction phase of the western half starting February 24th, during which vehicles will need to use the eastern half, resulting in a corresponding narrowing of the municipal road. Li Liang, manager of the Second Branch of the Municipal Group, the project contractor, previously stated that the project's key tasks include repairing sewage pressure pipelines, upgrading the road surface structure, and simultaneously improving the rainwater and sewage pipeline network system.
While racing against the construction schedule, the construction unit implements the concept of green construction, reducing the impact of construction on the surrounding environment through measures such as dust suppression via water sprinkling. All construction personnel remain at their posts, focusing on their tasks amidst the roar of machinery, ensuring the smooth progress of the municipal road project. Upon completion, the Jiangbi Road municipal road renovation will effectively enhance the traffic capacity of the city's transportation network, better serving the travel needs of citizens.