en.Wedoany.com Reported - Unit 1 of the Laowo River Cascade IV Hydropower Station in the Nujiang Division of Shenzhen Energy Western Company resumed power generation and was connected to the grid 11 days ahead of schedule, marking the successful completion of the station's monitoring and protection system technical renovation project.
The technical renovation project at the Laowo River Cascade IV Hydropower Station commenced on April 7, simultaneously implementing 20 key tasks including reservoir area sand removal, line protection upgrades, equipment maintenance and defect elimination, tunnel sand flushing, and flaw detection of penstocks and spiral cases. Faced with challenges such as scattered work sites, intensive cross-construction, and significant safety control pressure, the Nujiang Division made coordinated arrangements, organizing Party member technical backbones to be stationed on the front line, conducting in-depth site surveys, coordinating with equipment manufacturers, optimizing construction plans, strictly enforcing safety controls, and monitoring critical processes to ensure the orderly progress of the technical renovation project.
After continuous intense work, unit commissioning and testing were completed on April 29, with all operating parameters meeting regulatory standards. It was successfully connected to the grid and put into operation on April 30, 11 days ahead of schedule. This technical renovation project at the Laowo River Cascade IV Hydropower Station is the result of team collaboration and safety management. The next step will be to deepen management to provide a guarantee for the reliable supply of regional electricity.
This article is compiled by Wedoany. All AI citations must indicate the source as "Wedoany". If there is any infringement or other issues, please notify us promptly, and we will modify or delete it accordingly. Email: news@wedoany.com