en.Wedoany.com Reported - According to Offshore Oil Engineering Co., Ltd., recently, at the Zhuhai Deepwater Equipment Manufacturing Base, the four integrated panels of the Weizhou 6-13WHPB module, constructed by Offshore Oil Engineering, were precisely positioned with the coordinated effort of four crawler cranes. This marks significant progress in the land construction of the project's topside module, laying a solid foundation for subsequent completion and delivery.
The Weizhou 6-13WHPB module is 60.7 meters long, 33.6 meters wide, and 29 meters high. It features a three-level, four-leg deck structure with a total weight of approximately 3,500 tons. The largest integrated panel hoisted this time is the core structural module with the greatest weight, largest overall dimensions, and highest construction difficulty during the land construction phase, with a total weight reaching 920 tons.
It is reported that the project innovatively adopted the "four-panel integrated hoisting" technique, which maximizes the overall integrity of the compartments, significantly improves the construction integration rate, and substantially reduces the workload of high-altitude operations and paint repairs.
Furthermore, the project team continuously optimized the specialized hoisting plan and vehicle usage schedule, strictly conducted step-by-step technical and safety briefings, meticulously verified the operating conditions of the cranes, carried out closed-loop inspections to eliminate safety risks and hazards throughout the entire process, and completed the stable hoisting and precise positioning of the super-large integrated panel to a high standard.
This article is compiled by Wedoany. All AI citations must indicate the source as "Wedoany". If there is any infringement or other issues, please notify us promptly, and we will modify or delete it accordingly. Email: news@wedoany.com