Construction Begins on 99 MW Onshore Wind Project in Romania
en.Wedoany.com Reported - On November 24, energy group Premier Energy disclosed through the Bucharest Stock Exchange that its Romanian subsidiary Energia Mileniului III has commenced construction of a 99 MW onshore wind project near Războieni in Tulcea County. The project is expected to cost approximately EUR 140 million and will feature 16 wind turbines with a unit capacity of 6.2 MW each, with commercial operation planned for the end of 2028.

Premier Energy has signed a wind turbine supply and installation contract with Vestas Romania, along with a 20-year maintenance and availability guarantee agreement. The project will use Vestas V162 series wind turbines, with Vestas responsible for equipment supply, installation, and long-term operation and maintenance services.
For engineering, procurement, and construction, Premier Energy has signed an EPC turnkey contract with PORR Construct, which will undertake the engineering design, engineering services, construction, system testing, and commissioning of the entire wind farm. The wind turbine supply, installation, and long-term maintenance, and the overall wind farm construction are handled by the two contractors respectively.
According to the project development plan, the wind farm is expected to generate approximately 260 million to 290 million kWh annually, and upon completion will be incorporated into Premier Energy's renewable energy generation asset portfolio in Romania.