KONČAR of Croatia to Build 17.5 MW Shore Power System for Port of Rijeka
en.Wedoany.com Reported - On November 27, Croatian electrical engineering company KONČAR signed a contract worth EUR 11.4839 million (approximately RMB 83.8 million, excluding VAT) with the Rijeka Port Authority to design, construct, and install shore power systems for the Adriatic Gate Container Terminal (AGCT) and Rijeka Gateway container terminal at the Port of Rijeka. The total project investment is approximately EUR 15.5 million, of which 85% is provided by the EU Connecting Europe Facility and the remaining 15% by the Croatian national budget.

The works cover two container terminals. AGCT, located in Brajdica, will have a shore power system with a designed capacity of 10 MW; Rijeka Gateway, located in the Zagreb Pier area, will have a designed capacity of 7.5 MW. The two systems have a combined installed capacity of 17.5 MW and can supply power to two berthed container ships simultaneously.
Technical facilities include two dedicated substations, voltage and frequency conversion equipment, and cable management systems. The substations will convert shore-side power from 20 kV to 6.6 kV and convert the grid frequency from 50 Hz to the 60 Hz required by ships. Each terminal will be equipped with two 4 MVA shore power connection points, which can be combined into a single 7.5 MVA connection to meet the power supply needs of large container ships.
Once the systems are operational, container ships can use shore-side grid power directly while berthed at the terminal, shutting down their auxiliary engines and generators to reduce greenhouse gas emissions, particulate matter emissions, and noise. The Port of Rijeka will become the first port in the North Adriatic capable of providing shore power services to container ships, and will prepare its facilities in advance for the relevant shore power use requirements for ships that the EU will implement in the late 2020s.
Under the contract, the construction and commissioning period is 24 months, followed by 6 months of testing. Upon project completion, both AGCT and Rijeka Gateway terminals will have shore power connection capability for container ships.
Related Products



220kV Composite Outdoor Cable Terminal
Shenyang Guolian Cable Accessories Manufacture Co., Ltd.
Prefabricated Houses and Electrical Energy Boxes
Chengdu Ruilong Machinery Manufacturing Co., Ltd.

NISELA Series Environmentally Friendly Gas-Insulated Ring Main Unit
XJ DELISHIER ELECTRIC CO., LTD.
Oil-immersed Amorphous Alloy Core Distribution Transformer
Pinggao Group Smart Electric Co., Ltd.


0.66kV Power Supply Instrument Transformer
Guangdong Sihui Instrument Transformer Works Co., Ltd.
80kW Megawatt Supercharging Module TH80F10030C9
Shijiazhuang Tonhe Electronics Technologies Co., Ltd.
TAI Slew-drive Single-axis Independent 1P Tracking Bracket System
ANTAI TECHNOLOGY CO., LTD.








