Slovakia's Mochovce Nuclear Power Plant Unit 4 Raised to 35% Power

2026-11-16 14:38
Favorite

en.Wedoany.com Reported - At 2:35 a.m. on November 12, Slovenské elektrárne raised the reactor power of Mochovce Nuclear Power Plant Unit 4 to 35% of rated level, entering a new phase of the power start-up program. The unit has an installed capacity of 471 MW and has been conducting equipment and system tests since its first grid connection on October 15. As of November 8, the unit had generated a cumulative total of 16,184.77 MWh, with the next phase planned to raise reactor power to 55%.

Unit 4 is currently conducting equipment and system tests and parameter measurements at the 35% power level. The operator, in accordance with the established power start-up plan, is verifying equipment performance and system response under different operating conditions. The next power level can only be entered after the test results of the current phase have been evaluated.

Subsequent power increases will be implemented in the sequence of 55%, 75%, 90% and 100%, with corresponding operational tests and equipment inspections arranged at each stage. After completing the tests at each stage, the unit must also undergo a continuous 144-hour full-power verification run, operating continuously for 6 days at design parameters, as the final verification step of the power start-up program.

Unit 4 first delivered electricity to the Slovak grid at 20:41 on October 15. At that time, the reactor was operating at approximately 20% power, and the first of the two turbine generators was synchronized with the grid. Since then, the unit has continued to generate electricity while advancing power start-up tests. The cumulative electricity generation as of November 8 is equivalent to the annual electricity consumption of approximately 6,500 households.

Units 3 and 4 of the Mochovce Nuclear Power Plant both use VVER-440 pressurized water reactors, each with an installed capacity of 471 MW, totaling 942 MW. Once Unit 4 reaches full power and completes commissioning, it is expected to generate approximately 3.5 million MWh of electricity per year.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com