24-Hour Continuous Dredging Conducted at the Basin Fill Project of the ITS Terminal at the Port of Long Beach, USA
en.Wedoany.com Reported - On November 18, the latest construction progress was disclosed for the south basin fill project of International Transportation Service (ITS) at the Port of Long Beach, USA. The project site adopts a three-shift rotation system to carry out 24-hour continuous dredging operations every day. The construction team uses a derrick barge and large lifting equipment to conduct basin dredging, transporting the excavated sediment to the south basin of Pier G for backfill, which will subsequently form container yard land.

This operation is part of the Pier G South Slip Fill and the new G234 Berth construction project. The dredging work is undertaken by the Dutra Group, using the Morty derrick barge and Liebherr 8300 lifting equipment on site, supported by transport vessels and sediment transport barges. According to the U.S. Coast Guard 2026 45th Southwest District Local Notice to Mariners, Dutra Dredging is conducting dredging operations in the MC-1/MC-2 area of the West Basin at the Port of Long Beach from November 3 to February 1, 2027, with operations planned 7 days a week, 24 hours a day, and the site is equipped with the Morty derrick barge, PDC-2001 and PDC-2002 transport barges, the Lassen tugboat, and the Becky T anchor boat.
The basin fill project is invested in and constructed by International Transportation Service, with a total investment of approximately USD 365.19 million. The Dutra Group and Griffith Company form a joint venture to undertake project implementation, with an overall construction period from July 2025 to December 2028. The project expands the landside operating space of the container terminal by filling the existing south basin gap in the Pier G terminal area, and constructs the new G234 berth and rear yard facilities.
According to project construction materials, the fill project is expected to require approximately 2.6 million cubic yards (approximately 1.99 million cubic meters) of fill, cofferdam, and preloading materials. The construction scope includes demolishing two existing concrete wharf structures, G227 and G235, constructing temporary and permanent cofferdams, dredging and backfill, installing drainage boards, implementing surcharge preloading, and building a new concrete wharf and rear container yard. The new wharf shoreline will be extended by approximately 560 feet (approximately 171 meters), with supporting roads, lighting, power, and other utilities.
Beneficial reuse of dredged material is an important component of project construction. The project uses sediment generated from maintenance dredging in the port area for basin filling, while also receiving external harbor dredged material that meets environmental and engineering requirements. The Long Beach Harbor Commission previously approved the receipt of up to 225,000 cubic yards of third-party dredged sediment, including 185,000 cubic yards from Newport Bay and up to 40,000 cubic yards of dredged material from Balboa Yacht Basin. This approach reduces the reliance of some dredged sediment on offshore disposal sites and converts it into fill material for the wharf expansion project.
Upon completion, the ITS terminal will form a continuous berth and a larger-scale container yard, capable of simultaneously berthing two 18,000 TEU-class large container ships. The project owner expects that the expanded terminal's cargo handling capacity can be increased by up to approximately 50%. The project is currently still in the marine construction and landside construction stages, with overall completion planned for the end of 2028.
Related Products


Aoxuan Intelligent Precision Air Conditioning Unit
SHANGHAI AOXUAN PURIFICATION TECHNOLOGY CO., LTD.

YZR (450-560) Series Wound Rotor Three-Phase Asynchronous Motors for Crane and Metallurgical Applications
Jiamusi Electric Machine Co., Ltd.

Pure Polyurethane Wall Panel BD-AEF-PIR-01
Baodu International Engineering Technology Co., Ltd.




RISITA explosion-proof air conditioning
Guangdong RISITA Air Conditioning Equipment Co.,Ltd.