China State Construction Engineering Corporation Seventh Engineering Division Completes Breakthrough of Second Tube of 3.45 km Expressway Tunnel in Nepal

2026-11-19 10:27
Favorite

en.Wedoany.com Reported - On November 18, the second tube of the Mahadevtar Tunnel on the Kathmandu–Terai Fast Track (KTFT) in Nepal achieved breakthrough. The breakthrough ceremony was held in Makwanpur District and was attended by Nepalese President Ram Chandra Paudel, Minister for Physical Infrastructure and Transport Sunil Lamsal, and Zhou Pan, Minister-Counselor of the Chinese Embassy in Nepal. The tunnel tube is approximately 3.45 km long and was constructed by the International Company of China State Construction Engineering Corporation Seventh Engineering Division. It is a major controlling works of Package 1 of the fast track project. With this, excavation breakthrough has been completed for both parallel tubes of the Mahadevtar Tunnel.

The Mahadevtar Tunnel is located in the Makwanpur District section of the fast track and adopts a twin-tube, bidirectional traffic design. The other tube, heading toward Nijgadh, achieved breakthrough on September 3, 2026, while the second tube completed this time runs in the direction from Nijgadh to Kathmandu. The tunnel passes through complex geological conditions in mountainous areas, and construction was affected by multiple factors including fractured rock masses, geological variations, and the COVID-19 pandemic. The project team of China State Construction Engineering Corporation Seventh Engineering Division advanced the excavation through adjustments to construction organization and technical management, completing the excavation tasks for both tubes.

The tunnel is part of Package 1 of the Kathmandu–Terai Fast Track project. According to project contractor information, the scope of Package 1 includes approximately 8.69 km of expressway, approximately 1.074 km of bridges, and twin-tube tunnel works, with both tunnel tubes originally designed at approximately 3.35 km each. The project adopts an engineering, procurement, and construction (EPC) contracting model and is implemented by China State Construction Engineering Corporation Seventh Engineering Division. In May 2021, the Nepalese Army and China State Construction Engineering Corporation Seventh Engineering Division signed the contract for the tunnel and road works of Package 1.

The Kathmandu–Terai Fast Track has a total length of approximately 70.98 km, connecting Khokana in Lalitpur District with Nijgadh in Bara District. It is planned to include 7 tunnels with a total length of approximately 11.2 km and 89 bridges. The route passes through the mountainous areas of central Nepal. Once completed, it will form a rapid highway corridor from the capital Kathmandu to the Terai Plain in the south, improving road transport conditions between the capital and the industrial, agricultural, and border trade areas in the south.

According to data released by the Nepalese Army on November 18, the overall physical progress of the fast track project has reached 51%. Of the 14 tunnel tubes along the entire line, 6 have completed excavation breakthrough at three locations—Dhedre, Lendanda, and Mahadevtar—while the remaining 8 are still under construction.

After tunnel breakthrough, construction will move into the secondary lining and auxiliary structure phase, followed by waterproofing, pavement, and mechanical and electrical facility installation, as well as connection with adjacent road sections. A representative of China State Construction Engineering Corporation Seventh Engineering Division stated that subsequent work will accelerate the remaining construction and continue to strengthen project quality and safety management. This breakthrough completes the excavation task for the twin-tube Mahadevtar Tunnel under Package 1, but the entire fast track line remains under construction.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com