Thailand's State Railway Reassesses Budget of 35.807 Billion Baht for Procurement of 343 Railway Vehicles
en.Wedoany.com Reported - On November 18, the State Railway of Thailand (SRT) announced progress on adjustments to its railway vehicle procurement plan, proposing to procure 53 diesel-electric locomotives, 182 passenger carriages, and 108 air-conditioned diesel multiple unit (DMU) vehicles, totaling 343 vehicles across the three projects, with a budget of 35.8071 billion baht (approximately RMB 7.022 billion). Among these, the number of diesel-electric locomotives to be procured is proposed to be reduced from the original plan of 113 to 53, and the air-conditioned DMU vehicles from 184 to 108, while the procurement scale of 182 passenger carriages remains unchanged. At present, all three projects are still in the stage of investment feasibility assessment and procurement method evaluation.

According to SRT Governor Anan Phonimdang's briefing after the board meeting, the three procurement projects respectively target the replacement of aging locomotives, the renewal of express and special express passenger carriages, and the air-conditioned DMU vehicles required for commercial passenger services. Among them, the 53 diesel-electric locomotives have a budget of 11.130 billion baht (approximately RMB 2.183 billion), the 182 passenger carriages a budget of 10.5021 billion baht (approximately RMB 2.060 billion), and the 108 air-conditioned DMU vehicles a budget of 14.175 billion baht (approximately RMB 2.780 billion).
The locomotive procurement plan originally called for 113 units; after adjustment, the first batch is proposed at 53 units, mainly taking into account the actual condition of existing locomotives. SRT currently owns approximately 200 locomotives, including 20 new locomotives, 50 locomotives produced by CRRC Qishuyan, and 50 locomotives that have already undergone engine replacement, with approximately 130 aging locomotives still requiring gradual replacement. The adjustment of the procurement quantity to 53 units is the result of recalculation based on current vehicle renewal needs.
The 182 passenger carriages are mainly intended to replace existing express and special express train carriages, with a project budget of 10.5021 billion baht, including related spare parts. The air-conditioned DMU vehicles mainly serve commercial passenger routes; the original plan was to procure 184 units, currently proposed to be reduced to 108, with a budget of 14.175 billion baht. The two types of vehicles will respectively undertake the tasks of renewing existing passenger carriages and supplementing air-conditioned DMU capacity.
SRT is currently working with Thailand's Public Debt Management Office (PDMO) to study different procurement methods including direct purchase, leasing, and financial leasing, comparing the financing costs, interest burdens, and long-term financial impacts of each option. The project consultant submitted an interim feasibility study report on October 20, 2026, and the complete study report is planned to be submitted to the SRT board for review in January 2027. Under the current arrangement, the relevant procurement contracts are planned to be signed in 2028, with vehicles scheduled for phased delivery from 2029 to 2032.
In addition to the aforementioned procurement of 343 vehicles, SRT is also advancing a procurement project for 946 container freight wagons with a budget of 2.460 billion baht (approximately RMB 482 million). The relevant budget has been secured, and tender documents are currently being prepared, price benchmarks determined, and opinions on the tender documents solicited. According to the procurement plan previously approved by the Thai Cabinet, these freight wagons have a tare weight of 18 tons, a rated payload of 62 tons, and a maximum operating speed of 100 km/h, and can transport general containers, dangerous goods containers, and refrigerated containers. The vehicles are planned for phased delivery from 2029 to 2033, mainly serving railway transport between production bases, economic zones, and Laem Chabang Port, and undertaking cross-border freight transport among Thailand, Laos, and China.
At the same time, SRT has arranged 13 existing locomotive and vehicle repair, refurbishment, and modification projects, with a total budget of 6.69195 billion baht (approximately RMB 1.312 billion). The projects include 3 locomotive overhaul and replacement engine procurement projects, 3 DMU restoration projects, and 7 passenger carriage modification projects. The specific work involves locomotive engine replacement, DMU vehicle restoration, installation of air conditioning in ordinary passenger carriages, vehicle electrical system upgrades, and installation of enclosed sanitation systems.