Key Energy Project in Anhui Province! Unit 7 of Luohé Power Plant Phase IV Commissioned

2026-11-20 09:24
Favorite

en.Wedoany.com Reported - On November 19, Unit 7 of the 2×1000MW ultra-supercritical double-reheat coal-fired power project of Huainan Luohé Power Plant Phase IV, for which China Energy Engineering Group Southwest Electric Power Design Institute Co., Ltd. served as EPC general contractor and China Energy Engineering Group Building Group undertook construction, successfully completed its 168-hour full-load trial operation and officially entered commercial operation. As the first million-kilowatt coal-fired power project independently controlled and constructed by Huaihe Energy Holding Group, its completion and commissioning adds another clean and efficient power source support for Anhui Province and injects new momentum into energy security and supply for the Yangtze River Delta region.

Leading in energy efficiency, setting a new clean ceiling for coal power

As a key power source project in Anhui Province's 14th Five-Year Plan and an annual key dispatched project, Luohé Power Plant Phase IV aims at the goals of "industry-best energy efficiency and leading environmental protection indicators" and adopts the industry's advanced ultra-supercritical double-reheat power generation technology, making it a benchmark project for the clean and low-carbon transformation of traditional coal power.

The unit's main steam pressure exceeds 31MPa and its temperature exceeds 600℃. By adding an ultra-high-pressure cylinder to achieve two reheat cycles of steam, the designed standard coal consumption for power supply is as low as 256 grams per kilowatt-hour, approaching the highest level of coal power energy efficiency in China and reducing coal consumption per kilowatt-hour by about 15 grams compared with traditional single-reheat units.

It is simultaneously equipped with more than ten innovative technologies, including variable-frequency control of induced draft fan moving blades and integrated high-efficiency desulfurization and dust removal, and the emission concentrations of particulate matter, sulfur dioxide, and nitrogen oxides reach near-zero emission levels, breaking the stereotype of traditional coal power as "highly polluting."

Relying on the resource advantages of the Lianghuai coal base, the project deepens the coal-power joint operation model and realizes "mine-mouth power generation and local conversion." After full completion, the total installed capacity of Luohé Power Plant will leap from 1.9 million kilowatts to 3.9 million kilowatts, with annual power generation reaching 18 billion kilowatt-hours. It is expected to achieve an annual output value of 3.9 billion yuan and average annual tax revenue of 280 million yuan, continuously delivering reliable electricity to the Yangtze River Delta and helping Anhui build a UHV power hub in the Yangtze River Delta.

Lean fulfillment, expansion on the original site achieves accelerated fulfillment

The project implements capacity replacement construction on the original site of the decommissioned Phase I units without adding a single inch of construction land, fully reusing the old plant's public facilities, coal and water resources, and environmental protection indicators. It is a typical demonstration project of "building large units to replace small ones and upgrading on the original site."

The cramped site space was the number one challenge faced by construction: the core processing yard for Unit 7 was only 2,500 square meters and simultaneously served multiple functions including traffic passage, material turnover, and equipment hoisting, making the organization of the overall construction site plan far more difficult than that of conventional new-build projects.

The project team persisted in seeking space from existing resources, efficiency from process innovation, and schedule from refined control, launching a combined approach of lean fulfillment:

Revitalizing existing resources to expand space: repeatedly rehearsing the overall site plan and defining a three-stage dynamic site plan for the civil construction period, installation peak period, and project closeout period; proactively coordinating with the owner to convert the old plant's idle curved steel-frame dry coal shed into a dedicated assembly yard for boiler heating surfaces, which not only expanded working space and reduced weather impacts but also achieved efficient reuse of old plant assets and lowered temporary production facility costs. The project department established a regular overall site coordination mechanism, and the project manager personally led 57 special coordination and deployment meetings, strongly ensuring the efficient implementation of site use, machinery installation and dismantling, and other work, truly "doing the work within a snail's shell."

Process innovation improves quality and efficiency: for the hoisting of oversized components such as generator stators and intermediate-pressure cylinders, hydraulic lifting technology was innovatively adopted to replace the traditional direct crane hoisting scheme, compressing the hoisting time of a single large component from 72 hours to 36 hours and effectively shortening the duration of key processes. At the same time, the hoisting operation interfaces for deaerators and high- and low-pressure heaters were optimized, saving more than 800,000 yuan in costs; the near-live-line hoisting of 500kV GIL tubular busbars innovatively used the "long-distance hoisting plus near-distance transport with pulley track" process, safely avoiding the 220kV live area with a safe clearance of 7.185 meters and reducing costs by 33,000 yuan.

Digital control ensures milestones: schedules were reversed around key paths and operations were charted for battle. Relying on drone inspections and 720° panoramic imaging to build a visualized "aerial progress archive," a total of 8 schedule deviations were dynamically corrected, making production scheduling more precise and resource adjustment more efficient.

From the pouring of the first batch of concrete for the main powerhouse on December 25, 2024, to the 168-hour full-load trial operation, after 695 days and nights of continuous effort, the project achieved a 100% fulfillment rate of key milestone nodes: boiler steel structure hoisting started 32 days ahead of schedule, generator stator positioning was 33 days ahead, and turbine cylinder closing was 84 days ahead... Ultimately, Unit 7 achieved commissioning 36 days ahead of the contract schedule.

Quality and safety were strictly controlled throughout the entire process; construction proceeded safely for nearly 700 consecutive days, and the project was successively recognized as a power construction project safety and civilized construction site case, a typical case of smart construction sites in power construction, and a Level 1 power safety production standardization construction project, while its technical management and digital-intelligent construction achievements gained industry recognition.

Digital-intelligent empowerment, smart construction runs through the entire project cycle

As a project under upgraded management by China Energy Engineering Group, Luohé Phase IV runs digitalization and intelligence through the entire construction process, promoting the upgrade of project management from "experience-driven" to "data-driven."

Relying on the "Four Major Transformation Studios," the project formed four task forces for digital-intelligent management, BIM technology, drones and intelligent terminals, and AI and patented construction methods, practicing the concept of building digital models first and physical works second:

BIM models for five core specialties, including the main powerhouse and boiler steel structure, were successively completed; all-specialty collision detection eliminated hundreds of drawing errors, omissions, collisions, and missing items, reducing collision problems across the site by about 30% and avoiding rework losses at the source;

A three-level linkage system of "enterprise production command center—project smart control center—key operation area monitoring room" was built, integrating more than 40 functional modules, with more than 200 video surveillance channels linked to AI intelligent analysis, achieving 7×24-hour automatic identification and early warning for 12 types of violations;

Equipment such as intelligent welding robots was promoted and applied, realizing "mechanized replacement of people and automated reduction of personnel," with weld quality stability greatly improved;

A cloud-based file sharing system enabled real-time synchronization of engineering documents, with technical requirements reaching the front line of operations directly.

The in-depth application of digital technology has made on-site management more precise, scheduling more efficient, and safety more controllable, injecting strong scientific and technological momentum into the high-quality construction of million-kilowatt units.

Extended reading: 44 years of passing the torch, a new journey on the old site continues the glory

Luohé is an important birthplace of the Building Group's spirit of struggle and an important carrier of its "ultimate precision" culture.

In 1982, the Building Group undertook the construction of two 300,000-kilowatt units for Luohé Power Plant Phase I, which were then the thermal power units with the largest single-unit capacity in Anhui Province. The older generation of builders overcame difficulties under harsh conditions and forged the enterprise spirit of "unity and hard struggle, selfless dedication to public duty, courage to compete, and bravery to be an iron army," establishing the "four-no work style" of "no counting of time, no bargaining over conditions, no haggling over pay, and no discounting of standards." They achieved the outstanding result of commissioning Unit 2 168 days ahead of the national assessment schedule and won the National Quality Project Silver Award, and the name "Power Construction Iron Army" became widely renowned from then on.

In 1999 and 2007, the Building Group successively completed Luohé Power Plant Phase II and Phase III projects, and the "four refinements" philosophy and "ultimate precision" culture continued to settle and sublimate through repeated engineering practice.

Through 44 years of trials and hardships, from 300,000-kilowatt subcritical units to million-kilowatt ultra-supercritical double-reheat units, from shoulder-carrying and hand-pulling to digital-intelligent construction, what has changed is the equipment technology and construction methods; what has not changed is the original aspiration and mission of "bringing light to both banks of the Huaihe River." The Phase IV builders returning to the old site shoulder construction responsibilities with the original aspiration of cultural root-seeking, integrate the iron army spirit into the entire project construction cycle, and continue the construction bond spanning more than 40 years with premium projects. (China Energy Engineering Group Building Group, Yan Kailin)

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com