UK's Glen Rosa Ro-Pax Ferry Completes First Sea Trials and Enters Delivery Preparation Phase

2026-11-16 10:35
Favorite

en.Wedoany.com Reported - On November 12, the 102-meter LNG dual-fuel Ro-Pax ferry Glen Rosa, built by the Scottish shipyard Ferguson Marine, completed its first builder's sea trials in the Firth of Clyde. The vessel departed autonomously from the Inchgreen quay in Greenock and conducted tests in the waters between the Isle of Arran and the Isle of Bute, focusing on ship handling, navigation, automation, safety, power generation, and propulsion systems. Upon completion of construction, the vessel will be delivered to Scotland's ferry asset management body Caledonian Maritime Assets Limited (CMAL), with delivery currently scheduled for early February 2027.

Glen Rosa has an overall length of 102 meters and a gross tonnage of approximately 7,772 tonnes. It features an LNG and diesel dual-fuel propulsion system, can accommodate 852 passengers, and carry 127 cars or 16 heavy goods vehicles. The vessel is being built by Ferguson Marine for Scottish ferry operator CalMac and is planned to enter service on the Isle of Arran route, providing passenger and vehicle transport between the Scottish mainland and the islands.

These sea trials are builder's trials organized by the shipyard, with the focus on verifying the operational status of the vessel's main systems under actual sailing conditions. After the first round of sea trials, the shipyard will need to process the test data to address technical issues and complete subsequent equipment commissioning and construction closeout work. Thereafter, the vessel will undergo acceptance trials organized by the shipowner, focusing on verifying the dual-fuel propulsion system and related operational performance, ultimately completing regulatory approval and delivery formalities.

Propulsion system adjustments are a significant factor affecting the vessel's delivery schedule. Previous inspections identified cavitation issues with the ship's propeller blades, and the project decided to replace them with redesigned propeller blades during a drydocking period in January 2027. The replacement blades have already been delivered to the shipyard and are planned to be installed in sync with the drydocking maintenance work. Since the vessel cannot enter this type of drydock while loaded with LNG, LNG bunkering and system commissioning will be scheduled after the propeller replacement is completed. Currently, Glen Rosa continues to operate on diesel.

The propeller adjustments have also changed the originally planned delivery arrangements. The shipyard had previously planned to complete delivery in the fourth quarter of 2026; following rescheduling, the delivery date has been adjusted to early February 2027. After completing drydocking repairs, LNG system commissioning, and shipowner acceptance trials, CalMac will also organize berthing tests and crew familiarization training before the vessel can enter commercial passenger service.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com