China Railway Major Bridge Engineering Group Completes Cast-in-Place Girder Construction for All Superstructures of Le'an Yellow River Highway Bridge

2026-11-19 16:33
Favorite

en.Wedoany.com Reported - On November 17, the south bank floodplain approach bridge of Section 2 of the Binzhou Le'an Yellow River Highway Bridge, constructed by China Railway Major Bridge Engineering Group, completed its final concrete pour. The cast-in-place concrete girder construction for the entire bridge's superstructure has now concluded, and the project has entered the bridge deck system construction phase. This construction milestone involves the floodplain area on the south bank of the Yellow River and represents significant progress in the bridge's main structure construction.

The construction area of the Le'an Yellow River Highway Bridge has long been affected by Yellow River hydrological conditions, with soft floodplain foundations and high groundwater levels. Conventional cast-in-place construction on scaffolding is prone to uneven foundation settlement and scaffold deformation, which can affect box girder forming quality. During this cast-in-place girder construction, some box girders exceeded 40 meters in length, requiring the construction team to simultaneously control foundation bearing capacity, scaffold stability, and girder alignment.

To address the soft soil foundation and high groundwater level conditions, the project team adopted a composite support system combining steel pipe piles and Bailey beams. Before construction, the verticality, penetration depth, and pile top elevation of each steel pipe pile were inspected individually. After scaffold erection was completed, staged preloading was carried out to eliminate inelastic deformation of the scaffold, and formwork elevations were adjusted in reverse based on measured settlement data to determine girder pouring control parameters.

During concrete pouring, technical personnel continuously monitored scaffold settlement and Bailey beam deflection, tracking the support's stress state and structural deformation. Before each girder unit construction, the project department inspected scaffold component connections, stress conditions, and edge protection. After pouring was completed, scaffold removal and system conversion were carried out in accordance with construction specifications to control box girder forming alignment and structural quality.

The Le'an Yellow River Highway Bridge and approach road project has a total length of 18.9 kilometers, of which the Yellow River bridge is 3,834 meters long and the approach roads on both banks total approximately 15.07 kilometers. The project connects National Highway 220 to the north and Provincial Road S242 to the south. The main line is built to the standard of a two-way four-lane Class I highway, with a design speed of 80 km/h, a subgrade width of 25.5 meters, and a total investment of approximately 1.925 billion yuan.

Upon completion, the bridge will connect Danianchen Town in Huimin County, Binzhou City, with Taizi Town in Zouping City, changing the traffic situation in which the two areas have long relied on pontoon bridges to cross the river and had to take detours when ferry services were suspended during flood season. The construction plan previously disclosed for the project schedules completion for June 2027, with bridge deck system and related supporting works to continue.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com