en.Wedoany.com Reported - The Zhaoxian Guohui 150MW wind power demonstration project has now entered a full construction phase, with three core tasks—mixed tower pouring, wind turbine hoisting, and collector line installation—advancing simultaneously. Located in Fanzhuang Town and Xiezhuang Town, Zhaoxian County, Shijiazhuang City, the project is coordinated by Guoshun Technology Group, with CCCC Third Highway Engineering Co., Ltd. as the general contractor and China Energy Engineering Group Xinjiang Electric Power Design Institute Co., Ltd. responsible for supervision. Facing high summer temperatures and variable weather, the site ensures round-the-clock heavy transport corridor support and timely material delivery and inspection, while collector line laying is accelerated to create conditions for subsequent wind turbine grid connection.

Guoshun Technology Group provides overall coordination and fine-tuned scheduling, with management leading from the front, dynamically optimizing construction plans based on summer conditions, and increasing the frequency of safety hazard inspections. The supervision unit conducts item-by-item verification of key processes such as raw material delivery, sub-item acceptance, wind turbine hoisting, and equipment installation, and rectifies non-compliant operations.

The general contractor, CCCC Third Highway Engineering Co., Ltd., is responsible for construction organization, personnel deployment, and equipment maintenance, refining milestone plans and clarifying job responsibilities to achieve closed-loop management at the construction site. In the next phase, the project team will continue to strengthen safety and quality control, striving to achieve grid-connected power generation as planned.