China Galaxy Power Completes 1GW/4GWh Energy Storage Project in Xilin Gol League
2026-07-22 16:53
Favorite

en.Wedoany.com Reported - The construction general contracting project of the 1GW/4GWh independent energy storage power station in Xilin Gol League, undertaken by Galaxy Power for Envision Energy, was recently completed, marking a phased achievement in the construction of this large-scale energy storage project.

As the general contractor for the project, Galaxy Power coordinated on-site construction organization, safety management, quality control, and milestone delivery across key areas such as electrical installation, equipment installation, cable laying, grounding installation, commissioning, and testing, ensuring the project progressed safely, orderly, and with high quality through professional engineering services.

The Xilin Gol League Envision Energy storage project is large in overall scale and complex in system composition, covering multiple functional areas including the energy storage area, step-up substation area, and living area. The project's energy storage system consists of 199 sets of PCS integrated units and 796 sets of lithium iron phosphate battery prefabricated units, along with a supporting 220kV step-up substation and related electrical systems.

A large-scale energy storage power station is a complex power system engineering project. The station's internal electrical system involves multiple aspects including main transformers, 220kV AIS high-voltage equipment, 35kV power distribution systems, SVG reactive power compensation systems, energy storage equipment, secondary equipment, communication equipment, cable laying, grounding installation, commissioning, and testing.

During the project construction process, Galaxy Power focused on the requirements for key electrical system construction, strengthened on-site organization and professional coordination, and facilitated the smooth completion of equipment installation, system connection, commissioning, and testing, laying the foundation for the stable operation of the project.

From equipment installation to cable laying, from grounding construction to system commissioning, and from on-site management to testing and inspection, the project team implemented refined control over key aspects such as construction organization, safety management, and quality acceptance, ensuring the project progressed according to milestones and was delivered to standards.

The successful completion of the Xilin Gol League Envision energy storage project is an important practice for Galaxy Power in serving the new energy and energy storage sectors, and further demonstrates the company's comprehensive delivery capability in the field of large-scale power engineering construction general contracting.

Founded in 2006, Galaxy Power focuses on power engineering construction, operation and maintenance services, and preventive testing, with business covering power engineering up to 220kV, new energy and energy storage engineering, substation operation and maintenance, distribution operation and maintenance, and equipment testing.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com