en.Wedoany.com Reported - A foundation project to build an underwater base for the lock channel breakwater commenced in mid-February 2026.

This foundation forms the structural base of the breakwater, composed of sand and gravel materials particularly suited to marine conditions. Part of the sand and gravel comes from the beneficial reuse of dredged materials from the future navigation channel, placed via a diffuser barge supplied by a floating pipeline connected to transport vessels responsible for delivering the materials to the site.
HAROPA PORT stated that nearly 800,000 cubic meters of material have been placed along the 1,800-meter-long breakwater without any disruption to port commercial traffic.
The project is being executed by Terélian and its consortium partner DEME, under the supervision of HAROPA PORT.