Project Features:
-
China's largest refining and chemical integration project
-
Multiple single-train unit capacities broke records
-
Hoisting weights of multiple equipment items set historical records
Cumulative Completion:
-
1,781 equipment items hoisted, weighing 465,551 tons;
-
3,348 items unloaded at the wharf, weighing 305,988 tons;
-
273,000 square meters of foundation treatment.
Main Resources Deployed:
-
5000T hydraulic lifting device, XGC88000 4000-ton crawler crane, XGC28000 2600-ton crawler crane, CC8800-1 1600-ton crawler crane, CC8800 1250-ton crawler crane, XGC16000 1250-ton crawler crane, LR1750 750-ton crawler crane, SCC6500E 650-ton crawler crane, etc.