REC Unit Transfers Transmission Project to Adani
2025-02-13 15:06
Favorite

Wedoany.com Report-Feb 13, REC Power Development and Consultancy Limited has handed over the project specific special purpose vehicle (SPV) of the Rajasthan HVDC transmission project to Adani Energy Solutions Limited (AESL).

In a statement, the company said AESL was named the transmission service provider through tariff-based competitive bidding (TBCB) for development of the transmission project on build, own, operate, and transfer basis.

The implementation period of the project is 54 months.

This is the first HVDC transmission project, whereby the project is awarded to a private sector developer through the TBCB route.

The scheme covers establishment of 2 Nos. HVDC terminal stations of 6,000 megawatts at Bhadla (Rajasthan) and Fatehpur (UP), + 800 kV HVDC line (Hexa Lapwing) from Bhadla to Fatehpur (955 km) along with associated works.

The estimated cost of the project is around INR 22,700 crore.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com