To Open for Traffic by End of 2027! China's Lanzhou-Zhangye High-Speed Railway Station Buildings Begin Bidding
2026-04-07 14:56
Favorite

en.Wedoany.com Reported - On April 3rd, the bidding announcement for the general price-contract construction of the station building project and passenger service information project for the Wuwei to Zhangye section of the newly built Lanzhou-Zhangye Third and Fourth Railway Line was released. The station building project for the Wuwei to Zhangye section of the Lanzhou-Zhangye high-speed railway in China will officially commence construction at the end of May and is planned to be completed and open for traffic by the end of December 2027.

1. Bidding Conditions

This project has been approved for construction by the following documents: "Approval of the Feasibility Study Report for the Wuwei to Zhangye Section of the Lanzhou-Zhangye Third and Fourth Railway Line by China State Railway Group Co., Ltd. and the Gansu Provincial People's Government" (Tie Gai Fa Han [2024] No. 208), "Approval of the Preliminary Design for the Wuwei to Zhangye Section of the Newly Built Lanzhou-Zhangye Third and Fourth Railway Line by China State Railway Group Co., Ltd. and the Gansu Provincial People's Government" (Tie Jian Han [2024] No. 358), and "Approval of the Preliminary Design for the Jinchang South Station and Shandan North Station Buildings and Related Projects for the Wuwei to Zhangye Section of the Newly Built Lanzhou-Zhangye Third and Fourth Railway Line by China State Railway Group Co., Ltd. and the Gansu Provincial People's Government" (Tie Jian Han [2026] No. 46).

The project owner is Zhongchuan Railway Co., Ltd. The capital fund accounts for 70% of the total project investment, with China State Railway Group contributing 25.9% and Gansu Province contributing 74.1% (including land acquisition and demolition costs). Funds beyond the capital fund will be raised through debt financing such as loans from the China Development Bank.

The investment for the transfer corridor-related project under the Jinchang South Station platform will be borne by the Jinchang Municipal People's Government. The funds have been secured, the construction drawing design documents are complete, and the tenderee is the Lanzhou Engineering Construction Headquarters of China Railway Lanzhou Group Co., Ltd.

2. Project Overview

Construction Location: Jinchang City, Zhangye City.

Construction Scale: Newly built Jinchang South Station (7,997.65 square meters) and Shandan North Station (2,998 square meters) for the Wuwei to Zhangye section of the Lanzhou-Zhangye Third and Fourth Railway Line, along with related supporting projects such as water supply and drainage, HVAC, power supply, underpass decoration, and platform paving; civil engineering and supporting works for the transfer corridor under the Jinchang South Station platform.

3. Bid Package Division

(1) LZX-WZ-ZF Bid Package (Station Building Project)

Project Content: Construction of new Jinchang South Station and Shandan North Station buildings, along with supporting station building works, water supply and drainage works, HVAC works, power supply works, underpass decoration, etc.; civil engineering and supporting works for the transfer corridor under the Jinchang South Station platform.

(2) LZX-WZ-KFXX Bid Package (Passenger Service Information Project)

Project Content: Construction of new passenger service information systems for Jinchang South Station and Shandan North Station; office management information systems for production and living quarters along the line; public security management information system; video surveillance and access control system for the stabling yard; renovation of the passenger service system at Wuwei East Station, and other related works.

Planned Construction Period: 585 calendar days. Planned commencement date: May 20, 2026. Planned completion date: December 25, 2027.

It is reported that the Lanzhou-Zhangye high-speed railway is an important component of the national "Eight Vertical and Eight Horizontal" high-speed railway network's land bridge corridor and the Silk Road Economic Belt rapid passenger transport corridor, forming a second high-speed rail channel for the Lanzhou-Xinjiang corridor. The Zhongchuan Airport to Wuwei section has already been operational since the end of June 2024.

The newly built main line for the Wuwei to Zhangye section is 244.045 kilometers long, with bridges and tunnels totaling 121.013 kilometers, accounting for 49.59%. A 12.6-kilometer connecting line between the Lanzhou-Xinjiang Railway and the Lanzhou-Zhangye Third and Fourth Railway Line will be built in the Wuwei area. The design speed is 250 km/h, and the total preliminary design investment estimate is 26.74 billion yuan.

The entire line will have 6 stations, including 4 newly built stations: Zhuwangpu Station (overtaking), Jinchang South Station, Jiling West Station (overtaking), and Shandan North Station. Two existing stations will be connected: Wuwei East Station and Zhangye West Station.

The project officially commenced construction in December 2024 with a planned construction period of 3 years and is scheduled to be completed and open for traffic by the end of 2027. The construction of this project plays a significant role in further advancing the "Belt and Road" initiative and forming a large-capacity passenger transport corridor from Northwest China to Central and Eastern China. At the same time, it will effectively release the freight capacity of the existing Lanzhou-Xinjiang Railway, better serving the outbound transport of Xinjiang coal and safeguarding national energy security.