en.Wedoany.com Reported - Rosneft plans to technically launch the Vostok Oil pipeline project in 2026, having already commenced trial production at the Peschany block of the Paiyakh field and completed welding of over 700 kilometers of pipeline.

The project has fully welded and laid over 700 kilometers of pipeline to the design elevation, including a 422-kilometer dual-pipe section. Cleaning, calibration, and pneumatic testing of the pipelines are nearing completion. Construction of field stations for the external transportation system of the Vostok Oil project is in its final stages.
Regarding port facilities, the Severnaya Bukhta terminal is ready for vessel reception, featuring two cargo berths and one service vessel berth. The first oil loading berth is nearly finished, while filling and technical structure construction for the second berth are ongoing. The port infrastructure of the Vostok Oil project will support future crude oil exports.
This article is compiled by Wedoany. All AI citations must indicate the source as "Wedoany". If there is any infringement or other issues, please notify us promptly, and we will modify or delete it accordingly. Email: news@wedoany.com