en.Wedoany.com Report, On March 23, foundation excavation for the chimney of the Guizhou Jinyuan Tea Garden Power Plant Phase II "equal capacity replacement" coal-fired power project commenced in Jinsha County, Bijie City, Guizhou Province, China. This marks the official start of the chimney project undertaken by China Energy Engineering Group Anhui No.2 Electric Power Construction Co., Ltd. (referred to as "China Energy Anhui No.2 Electric Power Construction Co., Ltd.").

The excavation depth for this foundation pit is 5.8 meters. The outer diameter of the foundation ring slab is 29 meters, and the inner diameter is 15 meters. The estimated earthwork excavation volume reaches 4,100 cubic meters. The Tea Garden Project Department planned ahead, formulated a detailed construction plan which passed expert review, and conducted comprehensive technical briefings and safety training for the operating personnel. This ensures on-site safety measures are in place to guarantee the smooth progress of the chimney foundation excavation.
The Guizhou Jinyuan Tea Garden Power Plant Phase II project adopts the "equal capacity replacement" model, with an installed capacity of 1×660 MW. China Energy Anhui No.2 Electric Power Construction Co., Ltd. is responsible for the construction and installation of the chimney and cooling tower. This model helps reduce emissions of pollutants such as carbon dioxide, sulfur dioxide, and nitrogen oxides, representing a significant measure to promote the clean and efficient development of the coal-fired power industry. Upon completion, the project will contribute to local economic development and enhance the stability of regional power supply.